Students evaluated nuclear generation as a candidate subsystem within the Utah Power Grid.

The team compared capacity, reliability, licensing, schedule, water, environmental impacts, cost, grid integration, and public accountability rather than treating reactor technology as an isolated decision.

Graphic of Utah Power Grid
Utah Power Grid as the system of interest

Project Highlights

≥400 MWe

nearer-term dispatchable-capacity planning target.

~1 GWe

longer-horizon capacity objective.

8.45

AP1000 deterministic trade-study score.

Sep 2035

AP1000 Unit 1 planning-level commercial-operation milestone.

The Systems Decision

Why not just pick the reactor with the most power?

Because the strongest technology on one metric may still fail Utah's larger mission. The project treats schedule, licensability, grid integration, water, cost, supply chain, environmental stewardship, and public accountability as connected system concerns.

Graphic of Utah's existing generation mix shapes the decision
Utah Power Grid as the system of interest

From Statewide Need to Defensible Pathway

How Options Were Tested

The team did not rely on a single score. Each analytical layer answered a different part of the decision.

1

Frame the mission

Treat the Utah Power Grid as the system of interest.

2

Compare pathways

Use deterministic criteria for timeline, power/scalability, and regulatory maturity.

3

Test the calendar

Build planning-level deployment schedules to commercial operation.

4

Add uncertainty

Use Monte Carlo screening to expose fragility and viable regions.

The Deterministic Down-select

AP1000 · 8.45

Highest score; strong regulatory maturity and large single-unit capacity.

VOYGR · 7.80

Credible modular secondary pathway with staged expansion.

Natrium · 7.20

Flexible advanced pathway with licensing and HALEU uncertainty.

MARVEL · 5.95

Useful research platform, not a gigawatt-scale grid solution.

The project identifies AP1000 as the strongest near-term fit under the stated assumptions, while preserving modular light-water and advanced pathways as alternatives as conditions change.

Then Uncertainty Was Allowed Back In

25,000 MONTE CARLO SAMPLES

The stochastic model sampled a broad parameter space including power, core-size/geometry, enrichment, cost, and fuel-supply availability.

4.5% ALL-GATE SUCCESS

Only a small portion of the deliberately broad design space survived all technical and programmatic gates, showing why uncertainty matters.

Why Systems Thinking Changed The Answer

Schedule

A technically strong option can still arrive too late for the planning need.

Water

Utah's drought sensitivity makes water use and cooling posture first-order constraints.

Safety + Licensability

Foundational safety, regulatory credibility, and governance are treated as gates.

Grid Integration

Generation must connect to EMS/SCADA, protection, interconnection, and operational processes.

Lifecycle + Sustainment

Outages, workforce, fuel, maintenance, public reporting, and decommissioning remain part of the system.

Uncertainty

A fixed ranking is stress-tested to see whether the recommendation remains defensible as assumptions change.

Where Students Learn These Skills at ³Ô¹Ï¹ÙÍø

SE 6010

Foundations of SE

SE 6020

Project Management

SE 6130

Overview of SE Processes

SE 6140

Design for Feasibility

SE 6370

Requirements

SE 6500 / 6510

Senior Design Project

Connect It To The Profession & Career Readiness

COMMON REFERENCES

  • INCOSE Systems Engineering Handbook
  • ISO/IEC/IEEE 15288, 29148, and 42010
  • Kossiakoff and Blanchard systems engineering texts
  • MITRE Systems Engineering Guide

INCOSE VISION 2035 CONNECTION

  • Model-based and data-enabled decision making
  • Transdisciplinary systems engineering
  • Managing complexity and risk across the lifecycle
  • Systems engineering applied to major societal challenges

Keys to Capstone Success & How to Choose Your Project